Initial consultation.
Prior to filing a preapplication request under WAC
463-61-050, the preapplicant shall meet and consult with the EFSEC staff concerning the proposed project. Topics for discussion shall include but not be limited to:
(1) The nature of the project, the contents of the preapplication request and the status of the preapplicant's progress toward obtaining information and data regarding the project.
(2) A discussion of whether a third-party contractor is likely to be needed to prepare an environmental documentation for the project.
(3) Development of a preapplication plan to be filed with a preapplication request.
(4) The coordination of the public informational meeting.
[Statutory Authority: Chapter
80.50 RCW and RCW
80.50.040. WSR 08-21-092, ยง 463-61-040, filed 10/15/08, effective 11/15/08.]