HTML has links - PDF has Authentication
173-240-170  <<  173-240-180 >>   End of Chapter

PDFWAC 173-240-180

Approval of construction changes.

All wastewater facilities subject to the provisions of this rule must be constructed in accordance with the plans and specifications approved by the department. Any contemplated changes during construction, which are significant deviations from the approved plans, must first be submitted to the department for approval.
[Statutory Authority: RCW 90.48.110. WSR 00-15-021 (Order 00-09), § 173-240-180, filed 7/11/00, effective 8/11/00. Statutory Authority: Chapters 43.21A and 90.48 RCW. WSR 83-23-063 (Order DE 83-30), § 173-240-180, filed 11/16/83. Statutory Authority: RCW 90.48.110. WSR 79-02-033 (Order DE 78-10), § 173-240-180, filed 1/23/79. Formerly chapter 372-20 WAC.]
Site Contents
Selected content listed in alphabetical order under each group