Upon completion of the educational specifications and the site review by the superintendent of public instruction as provided for in WAC 392-342-020, the school district is authorized to proceed as follows:
(1) Commence with the design of the school facility in accordance with the district's educational specifications.
(2) Complete the energy conservation report pursuant to WAC 392-343-075.
(3) Complete a value engineering study and constructability review pursuant to WAC 392-343-080.
(4) Contract for building commissioning pursuant to WAC 392-343-080.
(5) Contract for construction management pursuant to WAC 392-343-102.
[Statutory Authority: RCW 28A.525.020. WSR 06-16-032, amended and recodified as § 392-342-040, filed 7/25/06, effective 8/25/06; WSR 99-24-046, § 180-26-040, filed 11/24/99, effective 12/25/99; WSR 98-19-140, § 180-26-040, filed 9/23/98, effective 10/24/98. Statutory Authority: RCW 28A.47.830. WSR 85-24-047 (Order 24-85), § 180-26-040, filed 11/27/85; WSR 83-21-065 (Order 10-83), § 180-26-040, filed 10/17/83.]