PDFWAC 51-11C-408012
Figure C408.1.4.1—Commissioning compliance checklist.
Figure C408.1.4.1
Commissioning Compliance Checklist
Project Name: | ||||
Project Information | Project Address: | |||
Certified Commissioning Professional: | ||||
Type of ISO Certification and Number: | ||||
Supporting Documents | □ | Manuals, record documents and training have been completed or are scheduled (Section C103.6) | ||
• | Building operations and maintenance information (C103.6.2) have been submitted to the owner or scheduled date: | |||
• | Manuals (C103.6.2.1) have been submitted to the owner or scheduled date: | |||
• | Compliance documentation (C103.6.3) has been provided to the owner or scheduled date: | |||
• | System operation training (C103.6.4) has been provided to the owner or scheduled date: | |||
Commissioning Plan | □ | Commissioning Plan was used during construction (Section C408.1.2) | ||
Commissioning Report | □ | Commissioning Report has been submitted (Section C408.1.3) | ||
Commissioned Systems | □ | Mechanical Systems were included in the commissioning process (Section C408.2) | ||
□ | Testing, adjusting and balancing is complete (Section C408.2.2). | |||
□ | There are unresolved deficiencies with the mechanical systems. These are described in the attached Commissioning Report submitted to the owner. | |||
□ | Service Water Heating Systems were included in the commissioning process (Section C408.3) | |||
□ | There are unresolved deficiencies with the service water heating systems. These are described in the attached Commissioning Report submitted to the owner. | |||
□ | Controlled receptacles and lighting control systems were included in the commissioning process (Section C408.4) | |||
□ | There are unresolved deficiencies with the electrical power and/or automatic lighting controls. These are described in the attached Commissioning Report submitted to the owner. | |||
□ | Additional Systems included in the commissioning process (Section C408.5) | |||
□ | There are unresolved deficiencies with systems required by Section C406 or Section C407. These are described in the attached Commissioning Report submitted to the owner. | |||
□ | Metering Systems were included in the commissioning process (Section C408.6) | |||
□ | There are unresolved deficiencies with the metering system. These are described in the attached Commissioning Report submitted to the owner. | |||
□ | Refrigeration Systems were included in the commissioning process (Section C408.7) | |||
□ | There are unresolved deficiencies with the systems required by Section C410. These are described in the attached Commissioning Report submitted to the owner. | |||
Certification | □ | I hereby certify that all requirements for Section C408 System Commissioning have been completed in accordance with the Washington State Energy Code, including all items above. | ||
Certified Commissioning Professional | Date | |||
□ | I hereby certify that all requirements for Section C408 System Commissioning have been completed in accordance with the Washington State Energy Code, including all items above. | |||
Building Owner or Owner's Authorized Agent | Date |
[Statutory Authority: RCW 19.27A.020, 19.27A.025, 19.27A.160 and chapter 19.27 RCW. WSR 19-24-040, § 51-11C-408012, filed 11/26/19, effective 7/1/20. Statutory Authority: RCW 19.27A.025, 19.27A.160, and 19.27.074. WSR 16-03-072, § 51-11C-408012, filed 1/19/16, effective 7/1/16. Statutory Authority: RCW 19.27A.020, 19.27A.025 and chapters 19.27 and 34.05 RCW. WSR 13-04-056, § 51-11C-408012, filed 2/1/13, effective 7/1/13.]