If an increase is not approved.

An agency request for an increase in funds may go to either the executive director or the board, as described in WAC 479-05-202, depending on the size of the request:
(1) If the executive director hears the request and does not approve it, the local agency may:
(a) Proceed with the project, paying for any additional costs with local or other funds;
(b) Withdraw the request for participation;
(c) Request a formal review of the executive director's decision by the board; or
(d) Submit a request to the executive director to reduce the scope of the project as provided in WAC 479-05-052.
(2) If the board hears the request and does not approve it, the local agency may:
(a) Proceed with the project, paying for additional costs;
(b) Withdraw the request for participation; or
(c) Request a scope modification or reduction as provided in WAC 479-05-052.
In either case, the project will need to retain a usable and functional improvement to be granted a scope reduction.
[Statutory Authority: Chapter 47.26 RCW. WSR 07-18-050, ยง 479-05-204, filed 8/30/07, effective 9/30/07.]