HTML has links - PDF has Authentication
296-127-180  <<  296-127-190 >>   296-127-200

PDFWAC 296-127-190

Filing of lien against retainage or bonds.

(1) Upon receipt of a timely complaint that a contractor has violated RCW 39.12.065, and that the contractor owes unpaid prevailing wages, the department may file a lien against the retainage or bond obtained by the contractor under RCW 60.28.011.
(2) Upon issuance by the director of a final decision that finds that a contractor has violated RCW 39.12.065 or 39.12.050, and that sets a civil penalty for the violation, the department shall file liens for the penalty amount against the retainage and bonds the contractor obtained under RCW 39.12.065 (2)(c), 39.08.010, and 60.28.011.
[Statutory Authority: Chapter 39.12 RCW. WSR 19-15-119, § 296-127-190, filed 7/23/19, effective 8/23/19. Statutory Authority: RCW 39.12.050, 39.12.065, 43.22.270 and 51.04.020. WSR 86-03-063 (Order 85-28), § 296-127-190, filed 1/17/86.]