Liability for failure to meet standards.

A member of the design or construction teams may not be held liable for the failure of a major facility project to meet the LEED silver standard or other LEED standard established for the project as long as a good faith attempt was made to achieve the LEED standard set for the project.
[ 2005 c 12 s 10.]