Informational filing requirement.
(1) A utility must file any voluntary RFP allowed under WAC
480-107-009(3) and accompanying documentation thirty days prior to accepting bids.
(2) If the utility must retain an independent evaluator under WAC
480-107-023, the utility must publish, on its public website, information explaining its independent evaluator selection process and commission approval process, including how interested persons can participate in the approval process.
[Statutory Authority: RCW
80.01.040,
80.04.160, and chapters
80.28, 19.280, and
19.405 RCW. WSR 21-02-023 (Docket UE-190837, General Order R-602), ยง 480-107-021, filed 12/28/20, effective 12/31/20.]