The stages of delayed projects.

For TIB funded projects, there are two stages of delay:
(1) Stage 1 delay - If the project does not meet the project target date per WAC 479-05-211.
(2) Stage 2 delay - If the project does not meet the revised bid date as agreed to under Stage 1 delay under WAC 479-05-213(1), or one year after being designated as a Stage 1 delayed project.