HTML has links - PDF has Authentication
480-108-080  <<  480-108-100 >>   480-108-110

PDFWAC 480-108-100

Dispute resolution.

An interconnection customer may ask the commission to review an electrical company's study costs, interconnection facility costs, system upgrade costs, deposit requirements, assignment of costs to the interconnection customer or an electrical company's processing, termination, denial or rejection of an interconnection application by making an informal complaint under WAC 480-07-910, or by filing a formal complaint under WAC 480-07-370.
[Statutory Authority: RCW 80.01.040 and 80.04.160. WSR 07-20-059 (Docket UE-060649, General Order 545), ยง 480-108-100, filed 9/27/07, effective 10/28/07.]