HTML has links - PDF has Authentication

Chapter 480-108 WAC

|Hide DispositionsLast Update: 6/7/23

ELECTRIC COMPANIESINTERCONNECTION WITH ELECTRIC GENERATORS

WAC Sections

HTMLPDF480-108-001Purpose and scope.
HTMLPDF480-108-005Application of rules.
HTMLPDF480-108-010Definitions.
PART 1: INTERCONNECTION OF GENERATION FACILITIES UNDER TIER 1, TIER 2, OR TIER 3 PROCEDURES
HTMLPDF480-108-015Scope of Part 1.
HTMLPDF480-108-020Eligibility and technical requirements for Tier 1, Tier 2, and Tier 3 interconnection.
HTMLPDF480-108-030Application for interconnection.
PART 2: GENERAL TERMS AND CONDITIONS FOR INTERCONNECTIONS
HTMLPDF480-108-040General terms and conditions of interconnection.
HTMLPDF480-108-050Completion of interconnection process.
HTMLPDF480-108-080Interconnection service tariffs.
HTMLPDF480-108-100Dispute resolution.
HTMLPDF480-108-110Required filingsExceptions.
HTMLPDF480-108-120Cumulative effects of interconnections.
HTMLPDF480-108-999Adoption by reference.
DISPOSITION OF SECTIONS FORMERLY CODIFIED IN THIS TITLE
480-108-035Model interconnection agreement, review and acceptance of interconnection agreements and costs. [Statutory Authority: RCW 80.01.040 and 80.04.160. WSR 07-20-059 (Docket UE-060649, General Order 545), § 480-108-035, filed 9/27/07, effective 10/28/07.] Repealed by WSR 13-15-089 (Docket UE-112133, General Order R-571), filed 7/18/13, effective 8/18/13. Statutory Authority: RCW 80.01.040 and 80.04.160.
480-108-055Dispute resolution. [Statutory Authority: RCW 80.01.040 and 80.04.160. WSR 07-20-059 (Docket UE-060649, General Order 545), § 480-108-055, filed 9/27/07, effective 10/28/07.] Repealed by WSR 13-15-089 (Docket UE-112133, General Order R-571), filed 7/18/13, effective 8/18/13. Statutory Authority: RCW 80.01.040 and 80.04.160.
480-108-060Required filings—Exceptions. [Statutory Authority: RCW 80.01.040 and 80.04.160. WSR 07-20-059 (Docket UE-060649, General Order 545), § 480-108-060, filed 9/27/07, effective 10/28/07; WSR 06-07-017 (Docket No. UE-051106, General Order No. R-528), § 480-108-060, filed 3/6/06, effective 4/6/06.] Repealed by WSR 13-15-089 (Docket UE-112133, General Order R-571), filed 7/18/13, effective 8/18/13. Statutory Authority: RCW 80.01.040 and 80.04.160.
480-108-065Cumulative effects of interconnections with a nameplate capacity rating of 300 kW or less. [Statutory Authority: RCW 80.01.040 and 80.04.160. WSR 07-20-059 (Docket UE-060649, General Order 545), § 480-108-065, filed 9/27/07, effective 10/28/07.] Repealed by WSR 13-15-089 (Docket UE-112133, General Order R-571), filed 7/18/13, effective 8/18/13. Statutory Authority: RCW 80.01.040 and 80.04.160.
480-108-070Scope of Part 2. [Statutory Authority: RCW 80.01.040 and 80.04.160. WSR 07-20-059 (Docket UE-060649, General Order 545), § 480-108-070, filed 9/27/07, effective 10/28/07.] Repealed by WSR 13-15-089 (Docket UE-112133, General Order R-571), filed 7/18/13, effective 8/18/13. Statutory Authority: RCW 80.01.040 and 80.04.160.
480-108-090Alternative interconnection service tariff. [Statutory Authority: RCW 80.01.040 and 80.04.160. WSR 07-20-059 (Docket UE-060649, General Order 545), § 480-108-090, filed 9/27/07, effective 10/28/07.] Repealed by WSR 13-15-089 (Docket UE-112133, General Order R-571), filed 7/18/13, effective 8/18/13. Statutory Authority: RCW 80.01.040 and 80.04.160.
Site Contents
Selected content listed in alphabetical order under each group