HTML has links - PDF has Authentication
480-107-017  <<  480-107-021 >>   480-107-023

PDFWAC 480-107-021

Informational filing requirement.

(1) A utility must file any voluntary RFP allowed under WAC 480-107-009(3) and accompanying documentation thirty days prior to accepting bids.
(2) If the utility must retain an independent evaluator under WAC 480-107-023, the utility must publish, on its public website, information explaining its independent evaluator selection process and commission approval process, including how interested persons can participate in the approval process.
[Statutory Authority: RCW 80.01.040, 80.04.160, and chapters 80.28, 19.280, and 19.405 RCW. WSR 21-02-023 (Docket UE-190837, General Order R-602), ยง 480-107-021, filed 12/28/20, effective 12/31/20.]