HTML has links - PDF has Authentication
296-150T-0340  <<  296-150T-0350 >>   296-150T-0380

PDFWAC 296-150T-0350

What must the test procedures and results for design plans include?

(1) Tests to a design for a factory-built temporary worker housing structure must be witnessed by a professional engineer or architect licensed in Washington state.
(2) Test reports must contain the following items:
(a) A description of the methods or standards that applied to the test;
(b) Drawings and a description of the item tested;
(c) A description of the test set-up;
(d) The procedure used to verify the correct load;
(e) The procedure used to measure each condition;
(f) Test data, including applicable graphs and observations of the characteristics and behavior of the item tested; and
(g) Analysis, comments, and conclusion.
(3) The written test procedures, results and conclusions must reference the applicable design plan.
[Statutory Authority: RCW 43.22.480. WSR 99-12-079, ยง 296-150T-0350, filed 5/28/99, effective 6/28/99.]