Construction oversight and testing.

The design engineer or the engineer's authorized representative shall:
(1) Conduct inspections to:
(a) Verify LOSS construction and materials conform with approved plans and specifications; and
(b) Collect data for the record drawings.
(2) Inspect the following:
(a) Poured-in-place sewage tanks construction;
(b) Installation of proprietary and public domain treatment and dispersal components;
(c) Installation of LOSS components in difficult conditions including, but not limited to, steep slopes and shallow soils; and
(d) Placement of sand or other fill material.
(3) Conduct or witness LOSS component testing to verify that all results fall within acceptable limits:
(a) Water tightness testing of all tanks under WAC 246-272B-05200; and
(b) Pressure testing of all new collection and conveyance piping according to an acceptable industry standard; and either
(c) Pressure and flow testing of the subsurface drip system to verify it functions properly prior to scheduling a LOSS final inspection by the department; or
(d) Pressure testing of the drainfield to verify it functions properly prior to scheduling a LOSS final inspection by the department.
(4) Record baseline pressure and flow information and provide passing results to the department during the final inspection.