At a minimum, the prospectus must contain information on the following elements:
(1) The goals and objectives of the project;
(2) Location including city or county, proximity to existing roads and other landmarks, and a vicinity map showing location of the proposed site(s);
(3) A statement of how the bank meets any watershed restoration needs and how its design and location are ecologically appropriate;
(4) The rationale for site selection addressing the considerations listed in WAC 173-700-303;
(5) The general need for the proposed bank project;
(6) General site map(s) that includes, but is not limited to:
(a) Total area of site;
(b) Location, size, and number of existing wetlands;
(c) Location of all streams, ponds, and other water features on or adjacent to the site;
(d) Location and type of all known water control features on or adjacent to the site; and
(e) Presence of rights of way, easements, or other encumbrances.
(7) A description of existing conditions of the proposed site(s) including, but not limited to:
(a) Land ownership;
(b) Local land use or zoning designation;
(c) Current use;
(d) Presence of liens, rights of way, easements, or other encumbrances;
(e) The landscape position of the site including water resource inventory area (WRIA), basin, and subbasin location;
(f) Wetland types present on the site including Cowardin classification and hydrogeomorphic (HGM) class of each wetland;
(g) Other habitat types present;
(h) Available information on water sources including surface water features, preliminary groundwater information, soil types, and vegetation;
(i) A preliminary analysis of functions provided by on-site wetlands;
(j) Adjacent land uses that might affect the bank's function;
(k) Site constraints, conflicts, or known risks that could affect bank development or function;
(l) Identification of all buildings, structures, and other built features that would remain on the site after construction; and
(m) Identification of existing mitigation sites and whether they will remain on-site after construction.
(8) Description of conceptual site design, including but not limited to:
(a) Proposed types and approximate sizes of wetlands;
(b) Other proposed habitat types to be provided;
(c) Proposed functions that the bank is anticipated to provide;
(d) Description of alterations to hydrology;
(e) Location of grading, if applicable; and
(f) Proposed structures (e.g., perch poles, weirs, trails, etc.).
(9) Figures illustrating the conceptual bank design;
(10) Proposed service area and accompanying rationale that demonstrates the service area is ecologically appropriate;
(11) Discussion of whether water rights have been applied for or secured for the site, if needed;
(12) Identification of proposed permanent protection mechanism, such as a conservation easement;
(13) The proposed ownership arrangements and long-term management strategy for the bank;
(14) Description of how the proposed bank project meets federal, state, and local laws and rules;
(15) Identification of whether the bank site is fully or partially located on agricultural lands of long-term commercial significance;
(16) The qualifications of the sponsor to successfully complete the proposed bank project(s), including information describing any past such activities by the sponsor; and
(17) The qualifications of the main design team and their areas of expertise.