PDFWAC 173-170-070
Criteria for approval of requests for financial assistance—Implementation phase.
(1) The implementation phase project(s) must be included in a comprehensive water conservation plan approved by the department.
(2) The agricultural water supply facilities must be designed to accomplish the purpose of the planned project. Accepted engineering design principles, criteria, and concepts will be used in the design of the facilities and approved by the department. Cost estimates for the proposed project must be prepared in detail. Plans and specifications must be approved by the department prior to advertising for construction bids.
(3) The State Environmental Policy Act (SEPA) requirements for any proposed actions must be met. The SEPA rules, chapter 197-11 WAC, will be followed to determine the environmental impacts of the proposed project. A copy of the final SEPA document and any needed supporting environmental analysis must be submitted to the department.
(4) Documentation showing all lands and land rights required for satisfactory construction, operation, and maintenance of the project have been or can be acquired.
(5) The project will not be in conflict with any applicable federal, state, and local laws, orders, regulations, rules, licenses, and permits.