82.94.030  <<  82.94.040 >>   82.94.050

Requirements for recipientsMeaningful construction.

(1) The recipient of a deferral certificate under RCW 82.94.030 must begin meaningful construction on an eligible investment project within two years of receiving a deferral certificate, unless construction was delayed due to circumstances beyond the recipient's control. Lack of funding is not considered a circumstance beyond the recipient's control.
(2) If the recipient does not begin meaningful construction on an eligible investment project within two years of receiving a deferral certificate, the deferral certificate issued under RCW 82.94.030 is invalid and taxes deferred under this chapter are due immediately.