57.22.030  <<  57.22.040 >>   57.22.050

PDFRCW 57.22.040

ReimbursementProcedures.

The procedures for reimbursement contracts shall be governed by the following:
(1) A reimbursement area shall be formulated by the board of commissioners within a reasonable time after the acceptance of the extension. The reimbursement shall be based upon a determination by the board of commissioners of which parcels would require similar improvements upon development.
(2) The contract must be recorded in the appropriate county auditor's office after the final execution of the agreement.
[ 1996 c 230 s 804; 1989 c 389 s 14.]

NOTES:

Part headings not lawEffective date1996 c 230: See notes following RCW 57.02.001.