PDFRCW 43.31C.050
Community empowerment zones—Amendment—Termination.
(1) The terms or conditions of a community empowerment zone approved under this chapter may be amended to:
(a) Alter the boundaries of the community empowerment zone; or
(b) Terminate the designation of a community empowerment zone.
(2)(a) A request for an amendment under subsection (1)(a) of this section may not be in effect until the department issues an amended designation for the community empowerment zone that approves the requested amendment. The local government must promptly file with the department a request for approval that contains information the department deems necessary to evaluate the proposed changes and its impact on the area's designation as a community empowerment zone under RCW 43.31C.030. The local government must hold at least two public hearings on the proposed changes and include the information in its request for an amendment to its community empowerment zone.
(b) The department shall approve or disapprove a proposed amendment to a community empowerment zone within sixty days of its receipt of a request under subsection (1)(a) of this section. The department may not approve changes to a community empowerment zone that are not in conformity with this chapter.
(3)(a) The termination of an area's designation as a community empowerment zone under subsection (1)(b) of this section is not effective until the department issues a finding stating the reasons for the termination, which may include lack of commitment of resources to activities in the community empowerment zone by the public, private, and community-based sectors. The local government may file an appeal to the department's findings within sixty days of the notice to terminate the area's designation. The department must notify the local government of the results within thirty days of the filing of the appeal.
(b) A termination of an area's designation as a community empowerment zone has no effect on benefits previously extended to individual businesses. The local government may not commit benefits to a business after the effective date of the termination of an area's designation as a community empowerment zone.
(4) The department may request applications from local governments for designation as community empowerment zones under this chapter as a result of a termination of an area's designation as a community empowerment zone under this section.
[ 2000 c 212 s 6.]