480-96-060  <<  480-96-070 >>   480-96-080

PDF

WAC 480-96-070

Reporting and Compliance.

(1) Clean energy compliance report. A large combination utility must file with the commission a clean energy compliance report as described in WAC 480-100-650 (1)(a) through (l) within six months of the end of each implementation period. As part of this report, a large combination utility must also:
(a) Include a summary of the steps taken to adaptively manage the large combination utility's portfolio and programs throughout the implementation period.
(b) Report electrification achievements using metrics consistent with subsection (3) of this section.
(c) Include a report of its work to comply with the requirements of RCW 80.86.030 during the last compliance period.
(2) Clean energy compliance report review process. The process for written comments, review, and determination of compliance will be conducted pursuant to the requirements in WAC 480-100-650(2).
(3) Annual clean energy progress reports. By July 1st of each calendar year, a large combination utility must file with the commission, in the same docket as its most recently filed ISP, an informational annual clean energy progress report regarding its progress in meeting targets during the preceding year. A large combination utility must make annual clean energy progress reports available on its website. These reports must include all of the requirements of WAC 480-100-650 (3) and (4), as well as the following information:
(a) Planned and claimed electrification achievement expressed as both the reductions in peak dekatherms per day, first year dekatherms, and lifetime dekatherms, and the associated increase in peak MW, and first-year MWh;
(b) A summary of the steps taken to adaptively manage the large combination utility's portfolio and programs throughout the preceding year;
(c) A summary of the large combination utility's efforts to comply with RCW 80.86.030;
(d) The renewable portfolio standard annual reporting requirements as described in RCW 19.285.070. To the extent these reporting requirements would be duplicative of requirements of the annual clean energy progress report, a large combination utility may provide a table that cites the specific place(s) within its annual clean energy progress report where renewable portfolio standard annual reporting requirements are met;
(e) Metrics used to track progress towards implementing the large combination utility's electrification of transportation plan, if applicable; and
(f) Metrics used to track customer benefit indicators.
[Statutory Authority: RCW 19.280.030, 19.280.040, 19.285.040, 19.285.080, 19.405.060, 19.405.100, 80.28.130, 80.01.040, 80.04.160, 80.28.365, 80.28.380, 80.28.425, chapter 80.86 RCW, and 2024 c 351. WSR 25-20-059 (Docket U-240281, General Order R-609), s 480-96-070, filed 9/26/25, effective 9/26/25.]