Upon final completion of the project by contractor(s), the architect/engineer shall inspect the project to determine compliance with the construction documents. The architect/engineer, upon determining that the project has been completed satisfactorily, shall make such recommendation through the issuance of a certificate of completion to the school district board of directors. Separate certificates of completion shall be written for each contract awarded. Certificates of completion shall provide a statement of work completed including the gross square footage of new and/or modernized construction per WAC 392-343-019.
Upon acceptance of project completion by the school district of directors, the school district is required to provide the office of superintendent of public instruction the board of director's resolution of acceptance and enter pertinent project data into the information and condition of schools data system. The office of superintendent of public instruction will determine the pertinent data to be provided.
[Statutory Authority: RCW 28A.525.020 and 28A.525.320. WSR 26-04-133, s 392-344-155, filed 2/4/26, effective 3/7/26. Statutory Authority: RCW 28A.525.020. WSR 06-16-032, amended and recodified as § 392-344-155, filed 7/25/06, effective 8/25/06; WSR 98-19-141, § 180-29-155, filed 9/23/98, effective 10/24/98. Statutory Authority: RCW 28A.47.830. WSR 83-21-067 (Order 12-83), § 180-29-155, filed 10/17/83.]