Dispute resolution.
An interconnection customer may ask the commission to review an electrical company's study costs, interconnection facility costs, system upgrade costs, deposit requirements, assignment of costs to the interconnection customer or an electrical company's processing, termination, denial or rejection of an interconnection application by making an informal complaint under WAC
480-07-910, or by filing a formal complaint under WAC
480-07-370.
[Statutory Authority: RCW
80.01.040 and
80.04.160. WSR 07-20-059 (Docket UE-060649, General Order 545), ยง 480-108-100, filed 9/27/07, effective 10/28/07.]