POTENTIAL SITE STUDIES

WAC Sections

HTMLPDF463-22-010Purpose.
HTMLPDF463-22-020Potential site study request—Where submitted.
HTMLPDF463-22-030Potential site study—Fee.
HTMLPDF463-22-040Potential site study—Contents.
HTMLPDF463-22-050Retention of consultant.
HTMLPDF463-22-060Notification of local authorities.
HTMLPDF463-22-070Independent consultant study—No preliminary approval.
HTMLPDF463-22-080Procedure where application precedes conclusion of study.
HTMLPDF463-22-090Additional costs procedure.
HTMLPDF463-22-100Public information meeting.


PDF463-22-010

Purpose.

This chapter sets forth procedures and guidelines for processing potential site studies pursuant to RCW 80.50.175.
[Statutory Authority: RCW 80.50.040 (1) and (12). WSR 04-21-013, § 463-22-010, filed 10/11/04, effective 11/11/04; Order 106, § 463-22-010, filed 11/4/76.]



PDF463-22-020

Potential site study request—Where submitted.

Requests shall be submitted to the energy facility site evaluation council at the council office in writing.
[Statutory Authority: RCW 80.50.040 (1) and (12). WSR 04-21-013, § 463-22-020, filed 10/11/04, effective 11/11/04; Order 106, § 463-22-020, filed 11/4/76.]



PDF463-22-030

Potential site study—Fee.

An initial fee of $10,000 shall accompany the study request and shall be a condition precedent to any action by the council. Payment shall be made by a cashier's check payable to the state treasurer.
[Statutory Authority: RCW 80.50.040 (1) and (12). WSR 04-21-013, § 463-22-030, filed 10/11/04, effective 11/11/04; Order 106, § 463-22-030, filed 11/4/76.]



PDF463-22-040

Potential site study—Contents.

A request for potential site study is to include a legal description of the proposed site, a general description of the area in which the proposed energy facility is to be located, and a description of the type, size, and significant features of the proposed facility itself. The council may require further information which it deems necessary to complete the request.
[Order 106, § 463-22-040, filed 11/4/76.]



PDF463-22-050

Retention of consultant.

Upon receipt of a request for a potential site study, the council shall commission an independent consultant of its choice to study and report in writing to the council on the potential site. The report of study shall set forth a general analysis of the potential environmental impact of the proposed energy facility and shall identify significant areas of environmental concern. The study may also encompass whatever other matters the council and potential applicant deem essential for an adequate appraisal of the potential site and potentially impacted areas surrounding or adjacent to the site.
[Statutory Authority: RCW 80.50.040 (1) and (12). WSR 04-21-013, § 463-22-050, filed 10/11/04, effective 11/11/04; Order 106, § 463-22-050, filed 11/4/76.]



PDF463-22-060

Notification of local authorities.

Upon receipt of a request for study of a potential site, the council will give notice to the legislative authority in each county, city and port district within whose boundaries the site of the proposed energy facility is located.
[Statutory Authority: RCW 80.50.040(1). WSR 78-09-080 (Order 78-7), § 463-22-060, filed 8/28/78; Order 106, § 463-22-060, filed 11/4/76.]



PDF463-22-070

Independent consultant study—No preliminary approval.

Nothing stated or recommended by the consultant, either during the study stage or in its report, shall be interpreted as preliminary approval or disapproval of the potential site by the council.
[Order 106, § 463-22-070, filed 11/4/76.]



PDF463-22-080

Procedure where application precedes conclusion of study.

In the event an application for certification is made prior to completion of the study, the council may terminate the study prior to completion.
[Order 106, § 463-22-080, filed 11/4/76.]



PDF463-22-090

Additional costs procedure.

The council shall provide the potential applicant an estimate of the full cost needed to complete the study including costs for consultants, council staff, council members, and other such expenses that are deemed reasonable by the council. In no event shall the study be allowed to continue if the potential applicant has not agreed to pay the cost thereof.
[Statutory Authority: RCW 80.50.040 (1) and (12). WSR 04-21-013, § 463-22-090, filed 10/11/04, effective 11/11/04; Order 106, § 463-22-090, filed 11/4/76.]



PDF463-22-100

Public information meeting.

During the potential site study, the council may hold a public information meeting in the county or counties within whose boundaries the site of the proposed energy facility is located, or as close to the proposed site as practicable. The council shall publish notice of the meeting in local daily or weekly news publications. This public information meeting shall not be in lieu of the requirements of RCW 80.50.090.
[Statutory Authority: RCW 80.50.040 (1) and (12). WSR 04-21-013, § 463-22-100, filed 10/11/04, effective 11/11/04.]