HTML has links - PDF has Authentication
296-870-30005  <<  296-870-30010 >>   296-870-30015

PDFWAC 296-870-30010

Initial installation and after major modification inspection and testing.

(1) You must make sure a completed powered platform installation has been inspected and tested by the building owner:
(a) Before it was first placed into service; and
(b) Before it was returned to service after major modification was done.
(2) You must make sure the inspection and tests determined that:
(a) All parts of the installation met the applicable requirements of this chapter; and
(b) All safety and operating equipment functioned as required.
[Statutory Authority: RCW 49.17.010, 49.17.040, 49.17.050. WSR 15-23-086, § 296-870-30010, filed 11/17/15, effective 12/18/15. Statutory Authority: RCW 49.17.010, 49.17.040, 49.17.050, 47.17.060. WSR 06-19-075, § 296-870-30010, filed 9/19/06, effective 1/1/07.]
Site Contents
Selected content listed in alphabetical order under each group