Review by affected states.
(1) Notice. The permitting authority shall give notice of each draft permit, permit revision, or permit renewal to any affected state on or before the time that the permitting authority provides this or permit revision notice to the public under WAC
173-401-800 and
173-401-805, except to the extent WAC
173-401-725 (2) or (3) requires the timing of the notice to be different.
(2) Response. The permitting authority, as part of the submittal of the proposed permit to the administrator (or as soon as possible after the submittal for minor permit modification procedures allowed under WAC
173-401-725 (2) and (3)), shall notify the administrator and any affected state in writing of any refusal by the permitting authority to accept all recommendations for the proposed permit that the affected state submitted during the public or affected state review period. The notice shall include the permitting authority's reasons for not accepting any such recommendation. The permitting authority is not required to accept recommendations that are not based on applicable requirements or the requirements of this chapter.
(3) British Columbia notification. The permitting authority shall notify British Columbia of draft permits, permit revisions, or permit renewals at sources located within 100 kilometers of the Washington-British Columbia border. Such notice shall be concurrent with notification of EPA and affected states.
[Statutory Authority: RCW
70.94.011,
70.94.161,
70.94.162,
70.94.331, and
70.94.510. WSR 16-05-003 (Order 13-12), § 173-401-820, filed 2/3/16, effective 3/5/16. Statutory Authority: Chapter
70.94 RCW. WSR 93-20-075 (Order 91-68), § 173-401-820, filed 10/4/93, effective 11/4/93.]